We were contracted by a mining company to sling tons of tin concentrate across a river in the DRC. We provided a Super Puma AS332L configured with cargo sling hook along with flight crew. Our crew provided ground training to the client’s riggers to ensure safe and efficient operations.
Democratic Republic of Congo – December 2019
Contract statistics
- duration: 6.5 weeks
- 1388 slings were carried out
- 2500 tons of tin concentrate were transported
- 168 hours were flown